POLK GYM FLOOR INTERIOR DEMOLITION
Polk, NE
PROJECT DETAILS:
CL Demolition crews completed an interior gym floor removal for High Plains Junior/Senior High School in Polk, NE, removing approximately 7,500 sq. ft. of hardwood flooring while preserving the original center-court logo. The work included interior demolition and disposal of multiple layers of wood flooring and the existing floating floor system, providing a clean slate for upcoming facility improvements.
PROJECT FEATURES:
• High Plains Jr/Sr High School in Polk, Nebraska
• Approx. 7,500 sq. ft. of hardwood gym flooring removed
• Interior demolition of two layers of tongue-and-groove wood flooring
• Removal of existing 2" x 4" floating floor system
• Preservation of center-court logo during demolition process
• Interior demolition completed in preparation for facility upgrades
• Safe, controlled demolition with minimal disruption to the facility